38m motoryacht paint re-inspection

2014/11/04

We inspected the paint on the hull topides of a 38m yacht which was re-delivered to the owner in April 2014. The reason for the inspection was to understand the eventual degradation of the applied (Dupont) paint system. Only small deficiencies were found which are being repaired under the warranty of the shipyard in the winter of 2015.